(SDLC INTERNAL USE ONLY)
Business
Objective:
Declare
the start of the project. This gate is used to kick-off finalization of the
feature set and project strategy.
Owner: Project
Sponsor
Review
Board:
N/A
Requirements:
|
ID
|
Description
|
Supplier
|
Receiver
|
Criteria
|
|
G12.R1
|
Project Sponsor
|
|
|
·
Assigned
|
|
G12.R2
|
Project Manager
|
|
|
·
Assigned
|
Business
Objective:
Approved
set of features and project strategy
Owner: Project
Manager
Review
Board: Project Sponsor, Project
Manager, Contracting Organization(s),
Performing Organization(s)
Requirements:
|
ID
|
Description
|
Supplier
|
Receiver
|
Criteria
|
|
G11.R1
|
Market Requirements for
Scope of Work
|
Contracting Organization(s)
|
Performing Organization(s)
|
·
Feature description reviewed and approved
|
|
G11.R2
|
High-level effort estimate
|
Performing Organization(s)
|
Contracting Organization(s)
|
·
Quick quote estimate available
|
|
G11.R3
|
Project Strategy
|
Project Sponsor(s)
|
·
Contracting Organization(s)
·
Performing Organization(s)
|
·
Project Strategy
·
Timeline
·
R&D budget
·
Affordability %
·
Releases to be included
·
Anchor objectives
|
|
G11.R4
|
G-11, G-10 and G-6 Review
Board
|
Project Manager
|
Review Board
|
·
Assigned
|
|
G11.R5
|
Previous Gates Passed
|
Project Manager
|
Review Board
|
·
Documented evidence that G-12 and G-11 requirements have
been satisfied
|
|
G11.R6
|
Management Review:
·
Project Strategy Decision
|
Review Board
|
·
Contracting Organization(s)
·
Performing Organization(s)
|
·
Approved strategy
|
Business
Objective:
Approve the scope of work for which the organization will commit to
develop requirements.
Owner:
Project Manager
Review
Board:
Project Sponsor, Project Manager, Contracting Organization(s), Performing
Organization(s)
Requirements:
|
ID
|
Description
|
Supplier
|
Receiver
|
Criteria
|
|
G10.R1
|
Initial portfolio scope
|
Contracting Organization(s)
|
Performing Organization(s)
|
·
Reviewed & approved
|
|
G10.R2
|
Project resource plan
|
Performing Organization(s)
|
Contracting Organization(s)
|
·
Preliminary resource plan
|
|
G10.R3
|
Business plan impact assessment
|
Contracting Organization(s)
|
Project Sponsor
|
·
Adjusted for high-level scope
|
|
G10.R4
|
Previous gates passed
|
Project Manager
|
Review Board
|
·
Documented evidence that G-10 requirements have been
satisfied
|
|
G10.R5
|
Management Review:
·
Project Scope Selection Decision
|
Review Board
|
·
Project Manager
·
Contracting Organization(s)
·
Performing Organization(s)
|
·
Consistent with the organization’s ability to deliver
|
Business
Objective:
Approve the plan to execute the definition phase so that the project’s
business requirements (scope, timeframe and cost) are met.
Owner:
Project Manager
Review
Board:
Project Sponsor, Project Manager, Contracting Organization(s), Performing
Organization(s)
Requirements:
|
ID
|
Description
|
Supplier
|
Receiver
|
Criteria
|
|
G9.R1
|
Plan
for the Definition Phase
|
Project
Manager
|
·
Contracting Organization(s)
·
Performing Organization(s)
|
For Definition Phase:
·
Detailed schedule
·
Resource/cost assigned
·
Capital budget developed
·
Risk plan developed
·
Scope defined
·
Quality plan defined
·
Configuration management plan defined
·
Communication plan defined
|
Business
Objective:
Approval of the system requirements definition(s) by the Contracting
Organization(s).
Owner:
Project Manager
Review
Board:
Project Manager, Contracting Organization(s), Performing Organization(s)
Requirements:
|
ID
|
Description
|
Supplier
|
Receiver
|
Criteria
|
|
G8.R1
|
System requirements
specification
|
Requirements
function of the PO(s)
|
Contracting Organization(s)
|
·
Inspected, approved and baselined
|
Business
Objective:
Completion of the estimates and scope refinement necessary for Lock-Down.
Owner:
Project Manager
Review
Board:
Project Manager, Contracting Organization(s), Allocation Function of the
Performing Organization(s), Development Function of the Performing
Organization(s)
Requirements:
|
ID
|
Description
|
Supplier
|
Receiver
|
Criteria
|
|
G7.R1
|
Estimation documentation
|
Allocation function of the Performing
Organization(s)
|
Development function of the Performing
Organization(s)
|
·
Allocated requirements, system interface and other
information necessary to perform estimation has passed design review
|
|
G7.R2
|
Refined resource estimates
|
Performing Organization(s)
|
·
Contracting Organization(s)
·
Development function of the PO(s)
|
·
Meets risk criteria necessary for Lock-Down
|
|
G7.R3
|
Final portfolio scope
|
Contracting Organization(s)
|
Performing Organization
|
·
Reviewed and approved, up to 100% of allocated affordability
|
|
G7.R4
|
WBS
|
Development function of the PO(s)
|
Project Manager
|
·
High-level
|
Business
Objective:
Obtain commitment between the Performing Organization(s) and the
Contracting Organization(s) for the delivery of a defined project scope of work
within a defined timeframe. (This scope is a refinement of the G-10 scope/plan).
Owner:
Project Manager
Review
Board:
Project Sponsor, Project Manager, Contracting Organization(s), Service
Organization
Requirements:
|
ID
|
Description
|
Supplier
|
Receiver
|
Criteria
|
|
G6.R1
|
Project plan (High-level)
with sufficient information to demonstrate the ability to deliver on the
commitment
|
Project
Manager
|
·
Contracting Organization(s)
·
Performing Organization(s)
|
·
High-level schedule developed through GA
·
Resource/cost profiles developed through GA
·
Capital budget approved
·
Risk plan developed
·
Scope defined
·
Quality plan defined
·
Configuration management plan defined
·
Communication plan defined
|
|
G6.R2
|
Deployment Plan
|
Contracting Organization(s)
|
Performing Organization(s)
|
·
FOA site(s) selected
·
CRO criteria defined
·
Cross product test traceability for system features
developed
·
Hardware requirements identified
·
HW/SW configurations to be deployed defined
·
Features to be deployed identified
|
|
G6.R3
|
Service Plan
|
Performing Organization(s)
|
·
Service Organization
·
Training Organization
|
·
Deployment tool impacts identified
·
Product training requirements defined
·
Documentation requirements defined
|
|
G6.R4
|
Business plan impact assessment
|
Contracting Organization(s)
|
Project Sponsor
|
·
Adjusted for final scope
|
|
G6.R5
|
G-4, G-2 and G-0 Review
Boards
|
Project Manager
|
Review Board
|
·
Assigned
|
|
G6.R6
|
Previous gates passed
|
Project Manager
|
Review Board
|
·
Documented evidence that G-9, G-8, G-7 and G-6 requirements
have been satisfied
|
|
G6.R7
|
Management Review:
·
Project Scope/ Cost/Schedule Commitment
|
Review Board
|
·
Project Manager
·
Contracting Organization(s)
·
Performing Organization(s)
|
·
Consistent with high-level plan
|
Business
Objective:
Approval of the detailed project plan and commitment of appropriate
resources to execute the plan.
Owner:
Project Manager
Review
Board:
Project Sponsor, Project Manager, Performing Organization(s)
Requirements:
|
ID
|
Description
|
Supplier
|
Receiver
|
Criteria
|
|
G5.R1
|
Project plan (Detailed)
with sufficient information to detail the assignment of work to
achieve the commitment
|
Development
function of the PO(s)
|
Project
Manager
|
·
G-6 High-level plan plus:
·
Detailed schedule
·
Resources assigned
|
|
G5.R2
|
Allocated requirements
|
Allocation
function of the PO(s)
|
Development
function of the PO(s)
|
·
Inspected and traceable to system requirements
|
|
G5.R3
|
System Interface
Specification
|
Allocation
function of the PO(s)
|
Development
function of the PO(s)
|
·
Inspected
|
|
G5.R4
|
Product Functional
Specifications
|
Requirements
function of the PO(s)
|
Development
function of the PO(s)
|
·
Inspected and traceable to system requirements
|
Business
Objective:
Ensure that the product meets the defined project scope and that the
quality of the product is at an acceptable level to proceed to the Validation
phase.
Owner:
Validation Function of the Performing Organization(s)
Review
Board:
Project Manager, Validation function of the Performing Organization(s),
Development Function of the Performing Organization(s)
Requirements:
|
ID
|
Description
|
Supplier
|
Receiver
|
Criteria
|
|
G4.R1
|
Product
|
Development function of
the PO(s)
|
Validation function of the
PO(s)
|
·
Contains all defined scope
·
Under Configuration Management
|
|
G4.R2
|
Test preparation complete
|
Validation function of the PO(s)
|
Validation function of the PO(s)
|
·
Lab configuration complete
·
Test tools available
·
Test cases available
|
|
G4.R3
|
Development testing results
|
Development function of the PO(s)
|
Validation function of the PO(s)
|
·
Agreed upon % run
·
Agreed upon % pass
·
Agreed upon open problems
|
|
G4.R4
|
System Integration results
|
Development function of the PO(s)
|
Validation function of the PO(s)
|
·
Agreed upon % run
·
Agreed upon % pass
·
Agreed upon open problems
|
|
G4.R5
|
Preliminary product documentation
|
Development function of the PO(s)
|
Validation function of the PO(s)
|
·
Install procedures complete
·
User documentation available
·
Previously known problems documented
·
Customer interface changes documented
·
Customer feature descriptions documented
|
|
G4.R6
|
Field performance criteria
|
Performing Organization(s)
|
Validation function of the PO(s)
|
·
Reviewed and approved
|
|
G4.R7
|
Previous gates passed
|
Project Manager
|
Review Board
|
·
Documented evidence that G-5 and G-4 requirements have been
satisfied
|
|
G4.R8
|
Management Review:
·
Go/No-Go Decision
|
Review Board
|
·
Project Manager
·
Validation function of
the PO(s)
|
|
Business
Objective:
Approve release of the
product to System Certification Testing.
Owner:
Contracting Organization(s)
Review
Board:
Project Manager, Contracting Organization(s), System Certification
Function of the Contracting Organization(s), Validation function of the
Performing Organization(s)
Requirements:
|